Free lightning safety plan template for construction sites

A fill-in-the-blank jobsite lightning safety plan you can complete in about 15 minutes, built around OSHA and NOAA lightning safety guidance for outdoor workers (OSHA 3863). It covers who watches the weather, when work stops, where crews shelter, and the 30-minute all-clear rule — plus a crew poster, an event log, and a training sign-off sheet ready to print.

Free to use and share. No email required.

How to use it: type directly into the blanks below and print, or download the Word version to keep on file. Appendix A (the crew poster) and Appendix C (the training sign-off) are designed to be printed and posted or passed around at orientation.

Jobsite Lightning Safety Plan

Based on OSHA / NOAA lightning safety guidance for outdoor workers (OSHA 3863)

1. Project information

Company
Project name
Site address
General contractor
Plan prepared by / title
Date prepared
Last reviewed

2. Purpose and scope

This plan establishes the procedures for suspending and resuming outdoor work at this jobsite when lightning threatens. Lightning is a recognized hazard for outdoor workers, and OSHA's General Duty Clause requires employers to protect workers from recognized hazards. This plan follows the practices recommended in OSHA and NOAA's joint guidance, Lightning Safety When Working Outdoors (OSHA 3863).

This plan applies to all employees, subcontractors, vendors, delivery drivers, and visitors on the site listed above. Every person on site is expected to know the stop-work signal and the location of the nearest safe shelter.

3. Roles and responsibilities

RoleNamePhone
Designated weather monitor (primary)
Weather monitor (backup)
Site superintendent (stop-work authority)
Safety manager

The designated weather monitor is responsible for watching lightning alerts and weather conditions during work hours and immediately notifying the superintendent when suspension criteria are met. The superintendent orders and announces the stop-work. Regardless of these assignments, any worker who hears thunder is authorized to stop their own work and move to shelter without waiting for instruction.

4. Weather monitoring

Work is suspended when lightning is detected within miles of the site (NOAA and OSHA guidance recommends 10 miles — thunder is generally audible to about that distance, and lightning can strike well away from the rain column). This distance is called the trigger distance below, and it is the radius referred to in Sections 5 and 7.

This plan requires that lightning be actively monitored during all outdoor work — meaning someone or something is watching continuously, not that a person checks a phone when the sky looks dark.

A monitoring method is adequate for this plan if it can do four things:

Capability required Why it matters
A Detect lightning at and beyond the trigger distance, near this specific site address The trigger distance is when your crew must already be clear — not when they start moving. Regional forecasts and radar don't tell you what's over your job.
B Notify the Designated Weather Monitor and crew leads without them having to check anything A method that depends on someone remembering to look is a method that fails on the busiest afternoons.
C Track the 30-minute all-clear countdown and restart it on each new strike This is the step most often skipped. Crews return early because nobody was timing it.
D Produce a written, timestamped record of each suspension and each all-clear Without a record, the plan cannot be audited, defended, or improved.

Any of the following can satisfy this plan. Whichever you choose, record it below and make sure A through D are covered — by the method itself, or by a person assigned to fill the gap.

Method Typical cost Covers A–B Covers C–D Practical limitation
Human observation — thunder heard, lightning seen Free Partial No Only detects storms already close. No record unless someone writes it down. Always required as a backstop regardless of other methods.
Free weather app or NWS radar on a phone Free Partial No Radar shows precipitation, not strikes. Requires someone to look. No timer, no log.
Handheld lightning detector $100–200 Partial No Detects nearby activity but range and accuracy vary. No notification, no timer, no log.
Software alerting service tied to the site address $29–60 per site / month Yes Yes Depends on cellular coverage and on contact lists being kept current.
On-site detection hardware with horn and strobe $5,000–15,000 per site installed Yes Varies Capital cost and installation. Usually justified only on long-duration or fixed sites.

5. Suspending work

5.1 Work stops when ANY of the following occurs

5.2 How crews are notified (check all that apply)

5.3 Order of shutdown

Shut down the highest-risk operations first. OSHA rules already prohibit scaffold work and crane hoisting during storms and high winds.

  1. Crane, hoisting, and rigging operations — land loads, secure the hook, and lower or secure booms per the manufacturer's storm procedure.
  2. Workers at height — scaffolds, steel erection, roofs, aerial lifts, and ladders.
  3. Open-cab equipment and workers in open areas — including flaggers and spotters.
  4. Make-safe steps for work that cannot stop instantly (e.g., a concrete pour in progress):
  5. All remaining outdoor work, then head to shelter.

Estimated time to make equipment safe and get all personnel into shelter: minutes. If this exceeds a few minutes, treat forecasted storms as the trigger to begin winding down high-risk work early.

6. Safe shelter locations

Acceptable shelter, in order of preference, per OSHA/NOAA guidance:

Not acceptable: sheds, canopies, tents, covered walkways, porta-johns, equipment with open cabs, scaffolding, and trees. Site office trailers are not assumed safe — treat a trailer as shelter only if it has been evaluated (grounded, wired, plumbed) and listed below.

Shelter locationType (building / vehicle)CapacityWalk time from farthest work area

If caught outside with no shelter reachable: avoid the tallest objects, open fields, water, and metal fences or rebar; do not shelter under trees or partially built structures.

7. Resuming work — the 30-minute rule

Work does not resume until 30 minutes have passed since the last lightning strike within the Section 4 radius (or the last thunder heard, whichever is later). Every new strike inside the radius resets the clock to a full 30 minutes. This is the NOAA standard reflected in OSHA 3863.

The all-clear is given by: , announced by: . No crew returns to work on their own judgment before the all-clear.

8. If a worker is struck by lightning

  1. Call 911. Give the site address from Section 1.
  2. Begin first aid immediately. Lightning strike victims carry no electrical charge and are safe to touch. If the person is not breathing or has no pulse, start CPR and use the AED.
  3. AED location: . Trained first aid / CPR personnel on site:
  4. If lightning is still active, move the victim to shelter before treating — rescuers in the open are themselves at risk.
  5. Report the incident to and preserve the event record. Work-related fatalities must be reported to OSHA within 8 hours; in-patient hospitalizations within 24 hours.

9. Training and communication

10. Recordkeeping

Each lightning event is documented: time of the first alert, how crews were notified, time of the all-clear, and total downtime. Records are kept by and stored at . Use the log in Appendix B, or the timestamped event reports generated automatically by your lightning alert service.

Appendix A — Crew poster (print and post)

⚡ LIGHTNING = STOP WORK
If you hear thunder or the stop-work signal, stop and get to shelter. Don't wait to be told twice.
Stop-work signal
Go to
Stay put 30 minutes after the LAST strike — every new strike restarts the clock
All-clear comes from — nobody goes back early
Weather monitor  · 
If someone is struck Call 911. They are safe to touch — start CPR immediately. AED:

Appendix B — Lightning event log

Skip this appendix if your alert service produces timestamped event reports automatically — file those instead.

DateAlert timeHow crews were notifiedAll-clear timeDowntimeMonitor initials

Appendix C — Training acknowledgment (print and sign)

I have reviewed the Jobsite Lightning Safety Plan for . I know the stop-work signal, the shelter locations, and the 30-minute all-clear rule, and I understand I am authorized to stop work and move to shelter if I hear thunder.

Name (print)Company / subcontractorSignatureDate

This template is provided by Lightning Ward free of charge to support your lightning safety program. It is general information, not legal, regulatory, or safety-engineering advice, and completing it does not by itself establish compliance with any law or standard. Adapt it to your site's conditions and have it reviewed by your safety professional. Primary sources: OSHA/NOAA, Lightning Safety When Working Outdoors (OSHA 3863); NOAA lightning safety guidance (weather.gov/safety/lightning).

Common questions

Is a lightning safety plan required by OSHA?

No, and here's what actually applies. There is no OSHA lightning standard and no rule that names a lightning safety plan, so nothing in the regulations tells you to write one. What applies instead is OSHA's General Duty Clause — the general obligation to keep the workplace free of recognized hazards — together with the joint OSHA/NOAA guidance Lightning Safety When Working Outdoors (OSHA 3863); separately, general contractors and project owners often require a written plan by contract even though OSHA does not.

What distance should trigger a work stoppage?

NOAA and OSHA guidance point to 10 miles, because thunder is generally audible to roughly that distance and lightning can strike well outside the rain column. Many contractors set their own trigger farther out, so crews have time to land loads and get down off steel before the 10-mile line is crossed. Whatever distance you choose, write it into the plan so it isn't being decided in the moment.

How long do you have to wait before resuming work?

Thirty minutes after the last lightning strike within your trigger distance, or the last thunder heard, whichever came later. Every new strike inside that radius restarts the full 30 minutes — it is not a countdown that keeps running through the storm. This is the NOAA standard reflected in OSHA 3863.

Do I need a lightning detector?

No single method is required, and no method is complete on its own. What the plan needs covered is detection at and beyond your trigger distance, notification that doesn't depend on someone remembering to look, a 30-minute clock that restarts on each strike, and a written record — Section 4 above compares the common options, free ones included, against those four. A handheld detector covers part of that; human observation stays a required backstop no matter what else you use.

Does a lightning policy apply to work inside a building?

A fully enclosed building with electrical wiring and plumbing is one of the two shelters this plan treats as safe, so crews already inside one are generally where you want them. The policy still applies to anyone who has to cross open ground between structures, work on a roof or an upper deck, or stand in an open bay or doorway. While sheltering indoors, stay off corded equipment and away from plumbing fixtures.

⬇ Download Word template (.docx) ⬇ Download PDF 🖨 Print this page

Free to use and share. No email required.

Sections 4, 5, and 7 can run themselves

The plan above depends on someone noticing lightning within 10 miles, notifying every crew, and timing 30 strike-free minutes — on every site, every storm, all season. Lightning Ward automates exactly that, and starts earlier: it watches out to 20 miles around your site address using professional strike detection, texts every contact with an advisory at 20 miles and a watch at 15, sends the stop-work alert when a strike lands inside 10, restarts the 30-minute clock on every new strike, and texts the all-clear when the window passes. Every event is logged in a timestamped compliance report you can hand to an inspector or project owner.